STAGE 1 2019-2025
Conversion, within six years, of an existing high-temperature steam network to a less energy-consuming, low temperature hot water system which entails:
Transition period
June 1, 2019 – March 31, 2020
Design and construction STAGE
June 1, 2020 – October 31, 2025
Operation & Maintenance of the existing system
April 1, 2020 – October 31, 2025
STAGE 2 2025-2055
Operation and maintenance of the new network until the end of contract.