There are two major phases to this 35-year contract:

2019-2025

Conversion, within six years, of an existing high-temperature steam network to a less energy-consuming, low temperature hot water system which entails:

Transition period
June 1, 2019 – March 31, 2020
Design and construction phase
June 1, 2020 – October 31, 2025
Operation & Maintenance of the existing system
April 1, 2020 – October 31, 2025

2025-2055

Operation and maintenance of the new network until the end of contract.

overview of main construction sites

Overview of main construction sites

Come back to this section often for the latest information about the construction work

Follow along throughout the construction period through social media and by signing up for our newsletter and SMS alerts (Standard text messaging rates apply).

Subscribe to newsletter and SMS alerts
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram